The Yellowhead Mainline Route Selection Process
Step 1 | Identify Need / Determine System Requirements [COMPLETE]
- Review system needs considering signed customer contracts and future growth requirements
- Identify and evaluate possible solutions to meet current and future system needs
- Determine required connection points and pipeline sizing
Step 2 | Generate Route Options [COMPLETE]
- The generation of route options is influenced by the following, in no particular order:
- Avoidance of environmentally sensitive areas
- Avoidance of areas which may present significant construction difficulties or the potential for long-term, ongoing maintenance or remedial work
- Parallelling existing linear infrastructure and other linear features such as utility corridors, roadways, railways, and property lines
- The overall length of the pipeline and associated construction costs
- Relatively direct path between required connection points
- For the Yellowhead Mainline Project, the "Routing Overview Map", dated February 26, 2024, represents the Route Options generated by this process
Step 3 | Evaluate Route Options and Select Preliminary Preferred Route [COMPLETE]
- An evaluation of each route option is conducted based on the following:
- Stakeholder early engagement (e.g. landowners, Indigenous communities, municipalities, counties, regulators, general public, etc.)
- Cost estimates
- Environmental impact
- Technical complexity, constructability and operational considerations
- Based on the evaluations, a Preliminary Preferred Route will be identified
- For the Yellowhead Mainline Project, the "Preliminary Preferred Route Map", dated February 21, 2025, represents the Preliminary Preferred Route
Step 4 | Assessment of the Preliminary Preferred Route [IN PROGRESS]
- Further consultation with the public, Indigenous communities, and landowners along the Preliminary Preferred Route
- Field assessments of the Preliminary Preferred Route (e.g. survey, environmental, geotechnical)
- Preliminary design completed for the Preliminary Preferred Route
- The Preliminary Preferred Route may change based on the results of these processes
Step 5 | Refinement and Confirmation of the Preferred Route
- The Preliminary Preferred Route may require further refinement as the project moves forward based on the results of more detailed engineering, additional field assessments, and additional landowner or stakeholder input
- The Preferred Route will be confirmed based on the refinement processes listed above
Step 6 | Application to the Alberta Utilities Commission (AUC)
- Once all application requirements have been met, ATCO will apply to the AUC for the Preferred Route, which could include some alternate routing segments
- Final route could change based on the results of the regulatory process