      Natural Gas System Upgrades

      Sometimes you will see us in your neighbourhood or within the Transportation Utility Corridor (TUC) completing work to upgrade the natural gas system. This work can be messy and kind of loud, but once we are done we will put things back the way found them.

      When we are working in your area it could be part of our Steel Mains Replacement (SMR) project in Edmonton and Calgary, our Plastic Mains Replacement (PMR) project in rural areas, or sometimes we are helping other major projects and moving our lines out of the way, such as through our Alley Renewal Program (ARP) in Edmonton. If by chance you do see us working near the ring road (also known as the TUC), we are likely out doing some work on the Urban Pipeline Replacement (UPR) Program.

      In most cases if you see our workers or contractors they are probably replacing old distribution lines with new pipelines for continued safe and reliable service for you the customer.

      How does this affect you?

      If you are going to be impacted by one of our projects, you will be contacted before any work takes place on your property by mail or by phone. ATCO representatives will meet with you to discuss specific impacts. To ensure you have proper notice of the work that will take place ATCO will notify all impacted homeowners prior to any construction activity or service interruptions.

      A few things that may happen if we are doing construction near your home or business:

      • Potential lane, road, alley or pathway closures
      • Increased traffic and construction noise
      • Excavation on your property near the gas meter and along boulevard to connect homes to the natural gas system
      • Temporary interruptions to your service, this will be arranged in advance with all residents
      • Increase in dust from construction

      To help ensure public safety, all our excavations that are open and accessible to the public will be supervised or fenced. We still ask that you please be aware of hazards and avoid excavation sites — especially keeping children and pets at a safe distance.

      If you have any questions

    • Calgary

      The projects listed below are active or soon to be active and will have direct impacts on customers. We will update this page as projects are about to start or when changes are required. 

      Calgary Downtown - 9 Avenue

       

      Construction Timeline: Q2-Q3 2025

      Location: 9th Avenue and Centre Street S

      Project: SMR

      Phase: In Construction

      Calgary McKnight

       

      Construction Timeline: Q3-Q4 2025

      Location: McKnight Blvd, Centre A Street NE and Trelle Drive NE

      Project: SMR

      Phase: Planning

      Calgary Downtown - 6 Avenue and 4 Street SW

       

      Construction Timeline: Q2 2025

      Location: 5 to 6 Avenue SW and 2 to 4 Street SW

      Project: SMR

      Phase: In Construction

    • Edmonton

      The projects listed below are active or soon to be active and will have direct impacts on customers. We will update this page as projects are about to start or when changes are required. 

      Dunluce Phase 1.5

       

      Construction Timeline: Q2 2025

      Location: 121 Street NW, and 162 Avenue and 162 A Avenue

      Project: SMR

      Phase: Ready for Construction

      Dunluce Phase 2

       

      Construction Timeline: Q2-Q3 2025

      Location: Dunluce Road, Warwick Road, and Warwick Crescent East of 127 Street NW

      Project: SMR

      Phase: Planning

      Meyonohk Phase 1

       

      Construction Timeline: Q3 2025

      Location: 78 Street to 89 Street, between 24 Avenue and Lakewood Road

      Project: SMR

      Phase: Planning

      Beverly Heights Phase 3

       

      Construction Timeline: Q2 2025

      Location: 118 Avenue NW from 50 Street to 36 Street, and 36-38 Street, from 104 Avenue to 118 Avenue

      Project: ARP

      Phase: Planning

      Landsdowne

       

      Construction Timeline: Q2 2025

      Location: 51A and 52 Avenue, east of 125 Street and 124 Street and Landsdowne Drive

      Project: ARP

      Phase: Planning

      156 Street

       

      Construction Timeline: Q4 2025

      Location: 156 Street and 112 Avenue

      Project: SMR

      Phase: Planning

      124 Street BIA

       

      Construction Timeline: Q2 2025

      Location: 124 Street and Jasper Avenue, and 123 Street and 102 Avenue

      Project: SMR

      Phase: In Construction

    • Other

      The projects listed below are active or soon to be active and will have direct impacts on customers. We will update this page as projects are about to start or when changes are required. 

      Mission (St. Albert)

       

      Construction Timeline: Q2 2025

      Location: St. Vital Avenue, Mill Drive, and Mission Place

      Project: ARP

      Phase: Planning

      St. Anne (St. Albert)

       

      Construction Timeline: Q3 2025

      Location: St. Anne Street, between Perron Street and St. Albert Trail

      Project: ARP

      Phase: Planning